top of page

ABOUT US

AIRFLOW INSTRUMENTATION was registered in 1983 due to the strong demand for cupola furnace automated airflow control systems- hence the name 'Airflow Instrumentation ' due to the decline in iron & steel works in 1992 we moved our business towards DCS (distribution control systems) & fire & gas commissioning services for offshore industry, mostly contracted to AOC Aberdeen later to become AOC Brown & Root, from 1992 todate our main work is oil & gas related such as:

MODU Projects Commissioning & Acceptance.

Power Plant Project Commissioning.

FPSO & Process Platform ICSS I&C construction/commissioning.

MODU SPS (Special Periodical Survey) 

MODU ready to drill acceptance

RECENT MODU COMMISSIONING & ACCEPTANCE PROJECTS.

JULY 2014

Ensco jackup rig E54,WBS

Specific Work Breakdown Structure (WBS)

Maintenance & Upgrade, Lamprell shipyard, Sharjah.UAE

Accountable for the coordination, administration and control

of Commissioning during Shipyard Project,

complete commissioning procedures specific for the project

upgrade for the rig as previous on Ensco projects.

​

FEBRUARY 2014

Ensco jackup rigs E96/E97 Five year SPS ( second stage )

(Special periodical survey),

Maintenance & Upgrade, N/KOM shipyard, Qatar.

Accountable for the coordination, administration and control

of Commissioning during both Shipyard Projects,

complete commissioning procedures specific for the project

upgrade for the rigs as previous on Ensco projects.

 

AUGUST 2013

Ensco jackup rig E88 Five year SPS

(Special periodical survey),

Maintenance & Upgrade, ASRY shipyard, Bahrain.

Accountable for the coordination, administration and control

of Commissioning during Shipyard Project,

complete commissioning procedures specific for the project

upgrade for the rig as previous on E94 project

 

FEBRUARY 2013

Ensco jackup rig E94 periodic survey, maintenance &

upgrade, ASRY shipyard, Bahrain. Accountable for the

coordination, administration and control of Commissioning

during Shipyard Project, complete commissioning procedures

specific for the project upgrades for the rig for;

Mooring and Marine Equipment, Cranes and Winches,

Drilling Equipment, Mud System, Well Control Systems,

Power Generation & Distribution, Safety and lifesaving,

Support Systems. CCTV, SIT. (System Integration & Test).

 

JULY 2012

Ensco drill ship DS-1 periodic survey, maintenance &

upgrade, Offshore Angola then onshore Cape Town in DCD

ship yard. 

Accountable for the coordination, administration and control

of Commissioning during Shipyard Project, complete

commissioning procedures specific for the project upgrades to

include; drawworks, crown block, travelling block, top drive,

dfma, sack cutting machine, shakers, screw cutting conveyors,

mud pumps, finger board, bridge racking crane, cement unit,

pipework renewals, stand pipe manifold, dsc, diverter system,

dead man system, choke manifold, bop controls, rov panel,

conduit valve manifold, Xmas tree crane/transporter, bulk

systems, iccp, valves replacements, lifeboats, thrusters, cranes,

SIT.

bottom of page